Vera Cruz Sewer Project Reaches Milestone Area III

Vera Cruz residents who live in the third phase of the Vera Cruz Sewer project received "hook-up" letters from the Lehigh County Authority this week.

When it came time for an update on the Vera Cruz Sewer Project at last night’s Board of Supervisor’s meeting, Supervisor George DeVault chimed in with a first-hand report.

DeVault, who lives in Milestone Area III, confirmed that homeowners in area III had received certified letters from the Lehigh County Authority earlier in the week, which basically said “you have until July 13 to hook up or else.”

Plus, DeVault said, grinder pumps have been delivered and can be seen in everyone’s backyards.

Find out what's happening in Emmauswith free, real-time updates from Patch.

Then, Upper Milford Township Manager Dan DeLong shared an update on the other milestone areas with the board:

  • Milestone Area I: Only homes has yet to be connected. This is the , DeLong said.
  • Milestone Area II: All but 14 homeowners have taken action to make their connection, he said.

“We had a spell of bad weather and that slowed things down some,” DeLong said, adding that the weather may have also been helpful in identifying potential problem areas.

Find out what's happening in Emmauswith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from Emmaus